Timeline & turnaround

How long it actually takes, stage by stage.

Total timelines already live on other pages. This breaks that total down by stage, so you know where the time actually goes. These are planning estimates, not a contract: your property and municipality decide the real number.

  • Feasibility
  • Drawings
  • Permit review
  • Construction
Time out my project

Where the weeks actually go.

  1. 01How busy is the building department?
  2. 02Is the application complete the first time?
Roughly 3–5 months~4.6 months
  1. Feasibility check1 wk
  2. Permit drawings3 wk
  3. Permit review7 wk
  4. Approval to start1 wk
  5. Construction8 wk
Start
Apr
Weeks
20
Ready around
Sep

Planning estimates, not a contract. Stages are shown end to end; some overlap in practice.

01

Two different project clocks.

Inside the house

Basement apartment

Separate building

Garden suite

Total3–5 monthsThe building already exists
Total6–12 monthsA new building, start to finish
Review4–10 weeksMunicipality dependent
Review8–16 weeksMunicipality dependent
Build6–10 weeksInterior work, any season
Build16–28 weeksFoundation to finishes
02

See where the time actually goes.

These are planning ranges. Your municipality, property and project scope can move the schedule. Review, highlighted, is the widest range on the page.

Basement apartment

Roughly 3–5 months

Faster path
  1. 01
    Feasibility checkProperty and code review
    About 1 week
  2. 02
    Permit drawingsBuilding + HVAC
    2–4 weeks
  3. 03
    Permit reviewMunicipality dependent
    4–10 weeks
  4. 04
    Approval to startFinal permit issue
    About 1 week
  5. 05
    ConstructionInterior build
    6–10 weeks

Some stages overlap in practice. Busier building departments can push review toward the top of its range or beyond.

Garden suite

Roughly 6–12 months

New build
  1. 01
    Feasibility checkLot, zoning and servicing
    1–2 weeks
  2. 02
    Drawings + servicing planBuilding + servicing
    4–8 weeks
  3. 03
    Permit reviewMunicipality dependent
    8–16 weeks
  4. 04
    Approval to startFinal permit issue
    1–2 weeks
  5. 05
    ConstructionFoundation, framing, services, finishes
    16–28 weeks

New construction has stages that can’t overlap: you can’t frame before the foundation cures, and servicing is inspected before it’s covered. That’s why a garden suite is measured in seasons, not weeks.

03

Totals aren’t simple addition.

Drawings, consultant work and contractor planning can sometimes move in parallel, and finishing touches on drawings can happen while early review comments come back. That’s why the total can be shorter than every stage added together.

Simple overlap example
  1. DrawingsWeeks 1 to 4
  2. Contractor pricingWeeks 3 to 5
  3. Permit reviewWeeks 5 to 12
The goal isn’t to rush the process. It’s to avoid dead time between stages.
04

The one stage we don’t fully control.

01

A complete application

Missing information is the single most common cause of delay, not a difficult reviewer.

02

Drawings built for the reviewer

Drawings that anticipate the review comments a specific municipality tends to raise, not a generic package.

03

Timing

Filing when a building department isn’t backlogged. It varies by season and by each municipality’s current workload.

We’ll give you a realistic review-time estimate for your municipality at the feasibility stage, based on what we’re currently seeing there.

05

Reduce avoidable waiting.

  1. Confirm feasibility first

    Before drawings. Don’t design a project that zoning, height or servicing can’t support.

  2. Keep decisions moving

    During drawings. Quick decisions stop small design questions holding the set.

  3. Submit a complete package

    Before submission. Missing documents create avoidable delays.

  4. Answer comments quickly

    During review. Fast, clear revisions keep the permit moving.

06

Pick the question closest to yours.

Have a property in mind?

A realistic timeline for your address.

For your specific property and municipality, not a generic one.